A Challenge

Tema Group Projects Include:

A Challenge

Following an urgent requirement from one of their customers Tema were awarded a contract for the turnkey supply of a Caustic Dosing Facility.

Although within the core skills of the team based in Cardiff the unusual challenge of a four-week lead-time from order placement to completed works was almost impossible.

However with careful planning a dedicated team the project was delivered in record time, after working day and night continuously the team hander over a successful completed plant.

MD Andy Marinos “although this appeared impossible with our commitment to the customer and the desire of the team to succeed we knew right from the start this was achievable, credit also has to be given to our suppliers who also went the extra mile.

Tema Groups Facilities Include:

Read More From Tema Engineering

Bam Nuttals

PROJECT: Q6 Olympic park Road bridge refurbishment 60 x 4.5 mtr span WHAT WE DID: The Bridge section was dismantled and delivered to Tema Protective coatings In house painting facility, Tema

Read More »

Bam Nuttals / Network Rail

PROJECT: Parson Pedestrian Foot Bridge / disabled access in South Wales 65mtr span & 12 no ramp sections. WHAT WE DID: Tema protective coatings applied a Network Rail N1 Paint Specification

Read More »
Numbers

Client results

Completed operations programs
0 +
Realized return on fees
0 x

Tema were always ready and keen to help where needed, with commitment to completing the order as quickly as possible, and exceeding expectations.

PROJECT ENGINEER -
GLOBALLY RENOWNED EQUIPMENT MANUFACTURER
Rated 5 out of 5

Discuss Your Engineering Project

We help companies stay ahead in a rapidly changing world.